Continental Diamond Tool is happy to report that construction on its new facility is progressing steadily. The building's exterior is almost complete. Finishing touches will be made to the interior of the building over the next several months, with completion slated for Spring 2018. 

CDT broke ground at their new facility in New Haven earlier this year. This expansion cost nearly $12 million. The new building will also make room for 77 additional jobs. 

The new 112,000 sq. ft. manufacturing facility will be equipped with state-of-the art equipment, allowing CDT to maintain their strong growth rate, better serve their customers and potentially double their employment base.

The project includes $5.25 million in manufacturing equipment, $400,000 in research and development equipment and $100,000 in information technology equipment.

If you or someone you know if looking for a new career opportunity, CDT is now hiring for the following positions: 

CNC programmersCNC operatorsCNC set upManual MachinistsElectroplatersDraftsmen (proficient in SolidWorks)

Click here to apply.

Company NewsGuest User